Jakarta Pushes Gerebek Lumpur to Face Rainy Season

Thursday, September 30th 2021 Reporter: Aldi Geri Lumban Tobing Translator: Nugroho Adibrata 1419

Pemprov DKI Kembali Lakukan Gerebek Lumpur Secara Serentak

(Foto: doc)

The Jakarta administration is pushing Gerebek Lumpur (mud cleanup) program in five city regions of Jakarta massively and simultaneously.

Today, we will dispatch around 408 personnel from five city regions plus 46 heavy equipment type amphibious excavator and 123 dump trucks

Yusmada Faizal, Jakarta Agency Head of Water Resources (SDA) said, it has been ongoing since March 24 for East Jakarta area. It would then be continued in 4 other city areas in stages from September to December.

To execute it, he stated, the agency has collaborated with the mayor, cross-agency, urban village, and sub-district in each region by deploying more heavy equipment to speed up the dredging of mud and garbage.

"Today, we will dispatch around 408 personnel from five city regions plus 46 heavy equipment type amphibious excavator and 123 dump trucks. This is targeted to be completed by the end of this year," he expressed, as quoted by Jakarta PPID's press release, Thursday (9/30).

He went on to say that it was carried out to minimize the volume of water during the rainy season in rivers and to smoothen the flow of water.

"We also need people to be more discipline not to litter and to keep the environment clean from puddles when it rains," he added.

The following is a detailed schedule and location of Gerebek Lumpur action in each region:

Central Jakarta

Location: Krukut River - Jalan Bendungan Hilir - Batavia Tower

Work: September 21 to December 31, 2021

Dredging yield target: 12,060 m3

Dumping Site in Ancol area

South Jakarta

Location: Krukut River - Jalan Jenderal Sudirman - Jalan Gatot Subroto

Work: September 9 to December 15, 2021

Dredging target: 5,338 m3 with 1.2 km length

Dumping site in Rawa Minyak

North Jakarta

Location: Sunter River, Front of Rawa Badak Pump and Front of Artha Gading Mall

Work: has started for about a month, targeted for completion in December 2021

Dredging target: Rawa Badak with 11,200 m2 width with a volume of 17,920 m3 and Artha Gading with 8,400 m3 width

Dumping site from Rawa Badak in Beting area and front of Artha Gading in Ancol

West Jakarta

Location: Mookervart River - Semanan - Rawa Buaya

Work: September 13, 2021 to December 2021

Dredging yield target: 36,000 m3

Dumping site in Ancol area

East Jakarta

Location: Munjul Reservoir

Work: March 24, 2021 to December 2021

Dredging target: for dredging the Munjul Reservoir with 44,197 m3

Dumping site at Bambu Apus TPU