Channel Dredging Work on Jalan Indo Karya 4 Completed

Wednesday, July 28th 2021 Reporter: Suparni Translator: Nugroho Adibrata 945

Saluran Air Sepanjang 176 Meter di Kelurahan Papanggo Dikuras

(Foto: Suparni)

The Tanjung Priok Sub-district Water Resources (SDA) Executing Unit, North Jakarta has completed dredging work on the 176-meter long water channel, Jalan Indo Karya 4, Papanggo Urban Village.

We have managed to pick up around 2,000 sacks from the channel

Tanjung Priok Sub-district SDA Executing Unit Head, Deny Tri Hendarto said, the channel was silting up with a mud thickness of up to 90 cm and prone to triggering puddles when it rained.

"We have managed to pick up around 2,000 sacks from the channel," he expressed, Wednesday (7/28).

To conduct it, he involved as many as 30 personnel to the location. "It is focused on Jalan Indo Karya 4 and has been carried out since last week," he stated.