Saturday, December 5th 2020 Reporter: Nurito Translator: Maria Inggita 1099
(Foto: Nurito)
Connecting channel construction which located on Jl. Raya Tengah, Tengah Urban Village, Kramat Jati, East Jakarta is targeted to finish within this week.
We are targeting to finish it this week
East Jakarta Water Resources (SDA) Sub-agency's Development and Drainage Improvement Section Head, Tengku Saugi Zikri mentioned, construction progress of this 433-meter channel has reached 95 percent or entering the finishing stage.
"We are targeting to finish it this week," he conveyed, Saturday (12/5).
In order to make this channel stronger and tidier, he installed it with concrete slab and U-ditch concrete with size 60x60 centimeters.
"Hopefully this channel can be functioned optimally thus it can prevent inundation and flooding in the area," he stated.