Thursday, April 2nd 2020 Reporter: Adriana Megawati Translator: Maria Inggita 1342
(Foto: Adriana Megawati)
Johar Baru Water Resources (SDA) Unit, Central Jakarta, deployed 10 personnel to repair Kawi-Kawi connecting (PHB) channel's retaining wall on Jalan Tanah Tinggi 1.
All materials used in this repair work are from Central Jakarta SDA Sub-department
Johar Baru Sub-district SDA Unit Head, Ru
di Prasetya stated, retaining wall that needs to be repaired has height of 7.5 meters and width of 3 meters. It was damaged because of being pushed by the roots of protective trees near the location."We break down the damaged part first, then build it with new material," he stated, Thursday (4/2).
His side is targeting to finish the repair next week. Besides Kawi-Kawi PHB channel, his side also repaired channel on Jalan Mardani Raya with length 116 meters and width 3 meters.
"All materials used in this repair work are from Central Jakarta SDA Sub-department," he closed.