Pluis Embankment Repair in Grogol Utara Finally Completed

Monday, February 3rd 2020 Reporter: Mustaqim Amna Translator: Nugroho Adibrata 1509

Perbaikan Turap Batu Kali PHB Permata Hijau Rampung

(Foto: Mustaqim Amna)

The repair of the collapsed Pluis connecting channel's embankment in RT 10/04, Grogol Utara Urban Village, Kebayoran Lama, South Jakarta, finally completed. 

Alhamdulillah the weather is pretty good so we can do repair faster before the target set for 30 days

"Its repair was executed on January 15 and finished today," said South Jakarta Water Resources Sub-agency's Maintenance Division Head, Junjung, Monday (2/3).

During the repair, the agency alerted around 10 officers and 1 dump truck to bring materials to the location.

He explained the embankment itself has 160 meters length with 4 meters height.

"Alhamdulillah the weather is pretty good so we can do repair faster before the target set for 30 days. Hopefully similar case can be anticipated later," he stated.

Bagikan ke :
BANG JAKI +indeks
POTRET JAKARTA +indeks
VIDEO +indeks

Hitung Mundur 22 Juni 2027

842
Hari
09
Jam
40
Menit
29
Detik