A connecting channel that is on Jalan Asem, RT 08/03, Pasar Minggu Urban Village, Pasar Minggu, South Jakarta is normalized.
We're doing repair up to 1.5 meters and 46 meters length
At the same location, the broken sheet pile is repaired in a bid to avoid landslides.
Pasar Minggu Sub-district Water Resources Executing Unit Head, Chairul Anwar stated that repair is carried out, as the river stone construction because of collapsed channel.
"We're doing repair up to 1.5 meters and 46 meters length," he expressed, Monday (12/3).
Pasar Minggu Sub-district Water Resources Executing Coordinator, Didi Supriadi added that similar action is also on the broken foundation up to 1 meter depth.
"Sheet pile and its foundation are old, and must be repaired to make it sturdier and not prone to landslides. The work takes approximately three weeks," he stated.