Tanah Abang Skybridge Construction Reaches 58 Percent

Friday, October 5th 2018 Reporter: Rezki Apriliya Iskandar Translator: Maria Inggita 1383

Pembangunan Jembatan Penyeberangan Multiguna Tanah Abang Capai 58 Persen

(Foto: Rezki Apriliya Iskandar)

Tanah Abang Skybridge construction has reached 58 percent per October 4, 2018.

We are optimistic to finish this project on target

PD. Pembangunan Sarana Jaya, Yoory C. Pinontoan said, skybridge construction which is started on August 3, 2018 is targeted to complete and ready to be used on October 15, 2018.

"Current progress is related to its structure construction, ceiling, precast for 2nd floor, fence on 1st floor, railing on 2nd floor, curb concrete for ramp area, and Block F and Block G connecting bridge," he explained, Thursday (10/4).

According to him, his side changes construction mechanism by constructing Zone D first and then continues to construct other zones thus the target can be achieved.

"We are optimistic to finish this project on target," he affirmed.