Thursday, November 6th 2025 Reporter: Anita Karyati Translator: Rizky Mawardi 112
(Foto: Istimewa)
Kelapa Gading District's Water Resources Unit, North Jakarta is improving the collapsed channel retaining wall in Boulevard Timur, Pegangsaan Dua Urban Village. The work is targeted for completion by the end of this month.
Now we're repairing the east side
Head of Kelapa Gading District's Water Resources Unit, Jhoni Sariyanto Situmorang said the retaining wall collapsed due to damage in several areas, coupled with persistent rain, leaving the retaining wall unable to support the soil.
"The south side was already repaired last year. Now we're repairing the east side," he said, Thursday (11/6).
He explained, the 2.5-meter-high retaining wall repairs are carried out over a 60-meter length. Nine Blue Taskforce personnel are deployed for the work.
"We also deploy one mini excavator to accelerate the work," he explained.
He added that the work has been running since November 3, 2025. The progress reaches 15 percent.
"After completing this work, we will dredge the channel," he added.
Head of Kelapa Gading District, Anita Permata Sari appreciated the work.
"Hopefully the new retaining wall will be able to hold the water especially during heavy rain," she hoped.