Thursday, November 23rd 2023 Reporter: TP Moan Simanjuntak Translator: Nugroho Adibrata 625
(Foto: Istimewa)
The West Jakarta Bina Marga Sub-agency repairs the damaged street, precisely at Jalan Padamulya, RW 08, Angke Urban Village, Tambora Sub-district.
It has reached 50 percent and will be completed today
Tambora Sub-district Bina Marga Executing Unit Head, Andry said the street repairs were carried out up to 500 square meters wide using hotmix asphalt.
"It is done to follow up on locals' proposal sounded in the Musrenbang forum," he expressed, Thursday (11/23).
According to him, the work involved 12 personnel completed with a milling machine. It will run for two days, precisely from November 22 to 23, 2023.
"It has reached 50 percent and will be completed today," he uttered.
The work received a positive response from RW 08 Angke Urban Village Head, Amir Syarifudin.
"Thank you for the fix," he stated.