Cilangkap Reservoir Dredging Progress Reaches 35 Percent

Friday, September 24th 2021 Reporter: Nurito Translator: Nugroho Adibrata 931

Pengerukan Waduk Cilangkap Capai 33 Persen

(Foto: Nurito)

The dredging progress of the Cilangkap Reservoir at RW 01 Cilangkap, Cipayung, East Jakarta, has now reached 35 percent.

It is carried out to overcome inundation in Cilangkap, Setu, Bambu Apus, etc

East Jakarta Water Resources (SDA) Sub-agency's Maintenance Division Head, Puryanto said, the reservoir was dredged to four to five meters depth using four heavy equipment consisting of one long arm and three standard units.

"It is carried out to overcome inundation in Cilangkap, Setu, Bambu Apus, etc," he expressed, Friday (9/24).

To smoothen it, the water in the reservoir was drained by closing the sluice gate bordering the reservoir in the Cilangkap Agro Tourism area.

He explained, the dredged mud was used to build inspection roads on the left and right of the reservoir with five meters width.

"It is expected to be completed by the end of this year," he stated.