Thursday, June 24th 2021 Reporter: Wuri Setyaningsih Translator: Maria Inggita 884
(Foto: Wuri Setyaningsih)
West Jakarta Water Resources (SDA) Sub-agency is currently repaired water channel on Jl. Flamboyan, Kebon Jeruk, by installing it with U-ditch and covers.
Our target is to complete it by the end of June
West Jakarta SDA Sub-agency Drainage Maintenance Section Head, Wawan Kurniawan mentioned, U-ditch and covers installation work has been carried out since June 12, 2021.
"U-ditch and channel co
vers will be installed on channel along 80 meters with width 60 centimeters," he informed, Thursday (6/24).His side deployed 1 unit mini excavator and 13 personnel equipped with hoes, crowbars, sledgehammers, hammers, and buckets.
"Current progress has reached 80 percent. Our target is to complete it by the end of June," he said.
He hopes this repair can optimize water channel capacity thus it can minimize inundation, especially during heavy rains.