Process of Tegal Alur Retention Basin Construction Reaches 70 Percent

Tuesday, November 10th 2020 Reporter: Rudi Hermawan Translator: Maria Inggita 1207

Pembangunan Embung Tegal Alur Sudah Mencapai 70 Persen

(Foto: Rudi Hermawan)

Tegal Alur Retention Basin construction in Kalideres, West Jakarta has reached 70 percent.

This retention basin is made to overcome inundation in Lokbin Tegal Alur due to local rain and tidal flood

West Jakarta Water Resources (SDA) Sub-agency's Flood Control Maintenance System for Clean Water and Wastewater Section Head, Wawan conveyed, this retention basin is as wide as 2,410 square meters and depth of 3 meters on 3,640 square meters land.

"This retention basin is made to overcome inundation in Lokbin Tegal Alur due to local rain and tidal flood," he said, Tuesday (11/10).

According to him, this retention walls can accommodate up to 7,230 cubic meters water to prepare for water runoff from Semongol River or tidal flood.

"We have started the construction since September and targeted it to finish in December," he closed.