The South Jakarta Water Resources Sub-agency develops a 300-meter length temporary embankment on Jalan Bina Marga, RW 07, Rawajati, Pancoran, which aims to anticipate flooding when it rains.
The work itself has been carried out since early October and is targeted to be complete in December
"The work itself has been carried out since early October and is targeted to be complete in December," expressed South Jakarta Water Resources Sub-agency's Maintenance Division Head, Junjung, Wednesday (10/30).
To do it, we send 60 personnel and one heavy equipment. The dam is made up to 1.5 meters height with 2 meters width.
"We help by making sand embankments and dolken frames to anticipate flooding during the rainy season," he stated