Monday, September 30th 2019 Reporter: Budhi Firmansyah Surapati Translator: Maria Inggita 1094
(Foto: Budhi Firmansyah Surapati)
North Jakarta Bina Marga Sub-department concretes 107 collector roads in six urban villages. This project is started in September and targeted to finish in December.
It is to follow up residents proposal on Musrenbang 2018
North Jakarta Bina Marga Sub-department's Bridge and Road Maintenance Section Head, Ujang Royani stated, each collector roads have different width and length. Those roads will be concreted with thickness around 25 centimeters.
"It is to follow up residents proposal on Musrenbang 2018. They asked to elevate the road because its condition is damaged and often submerged in puddles," he explained, Monday (9/30).
In detail, he continued, there are 15 collector roads in Penjaringan, 13 collector roads in Pademangan, 40 collector roads in Tanjung Priok, 14 collector roads in Koja, 10 collector roads in Kelapa Gading, and 15 collector roads in Cilincing Sub-districts.
According to him, this project is involving assistance and monitoring from North Jakarta District Prosecutor's Security Team for Government and Regional Development (TP4D), starts from its planning stage until finish.
"Total area that need to be concreted reaches around 161,474 square meters. Our target is to complete it in mid of this December," he conveyed.