Safety Barriers Reinforced at Rorotan Clean Water Pipeline Site

Thursday, November 19th 2026 Reporter: Anita Karyati Translator: Nugroho Adibrata 35

Proyek Pipa Air Bersih Rorotan 2 anita

(Foto: Anita Karyati)

Construction on the clean water pipeline network along Jalan Malaka I to III in Rorotan, Cilincing, North Jakarta, remains on track for completion in December 2026, with road user safety kept as a top priority throughout the works.

Now that pipe installation is complete, personel have moved into the hydrostatic pressure testing phase—a quieter stage with fewer visible workers on-site that had briefly led local residents to think the project had been halted.

The project hasn't stopped or stalled at all

Rorotan Urban Village Head Ahmad Fitroh explained that the site appears quiet simply as personnel are currently conducting hydrostatic pressure tests.

"The project hasn't stopped or stalled at all. That misunderstanding briefly sparked frustration among locals, to the point where some kicked safety barriers into the excavation trench," he expressed, Thursday (11/19).

Ahmad explained that this left several excavation trenches without proper safety barriers, posing a hazard to passing road users—especially motorists navigating around the work zone.

"To prevent any accidents, we immediately deployed Satpol PP personnel to retrieve the fallen barriers and secure the perimeter around the site," he explained.

He welcomed the public feedback and media coverage surrounding the project, emphasizing that community oversight helps keep contractors accountable for maintaining safety and cleanliness across the work zone.

"We appreciate the public's input as part of our ongoing evaluation, and we continue to press the contractor to restore the roadway on schedule," he continued.

PAM Jaya Senior Manager for Corporate and Customer Communication, Gatra Vaganza confirmed that the utility acted immediately on the open trenches and fallen barriers, issuing a formal reprimand to the contractor overseeing the site.

"We addressed it that same day. Our inspection found that the barriers tipped over easily as they hadn't been properly filled with water, leaving them unstable against weight or impact," he explained.

He added that the completion timeline was pushed back from October to December 2026 after local neighborhood permit hurdles forced the contractor to reroute sections of the pipeline and adjust on-site construction methods.

"Our original target was October, but it moved to December after several segments hit delays awaiting neighborhood clearances from local residents," he concluded.