Water channel normalization conducted on Jalan Kayu Manis IX, RT 04/08, Matraman, East Jakarta has reached 95 percent.
This normalization is targeted to complete on December 19
East Jakarta SDA Sub-department's Development Section Head, Tengku Saugi Zikri explained, his side has started to normalize that 724-meter channel since mid of October 2019.
"This normalization is targeted to complete on December 19," he stated, Sunday (12/15).
According to him, currently his side is installing U-ditch concrete with size 60x60 centimeters on the channel.
"We construct channel on Jalan Kayu Manis IX to connect with Kayumanis Timur connecting (PHB) channel," he informed.