Friday, November 8th 2019 Reporter: Nurito Translator: Maria Inggita 1401
(Foto: Nurito)
Caglak River bridge widening project on Jalan Lapangan Tembak, Cibubur, Ciracas, East Jakarta with total budget of Rp 1 billion now has reached 20 percent.
Its process has reached 20 percent
East Jakarta Bina Marga Sub-department Head, Muhammad Soleh explained, Caglak River bridge widening project has been started from one month ago. It is done to follow up resident's request through Musrenbang.
"Its process has reached 20 percent," he added, Thursday (11/7).
In this stage, his side has removed the utility network, put a few of hollow blocks into fabrication process, and prepared to install the piles on Friday (11/8)
"This project is targeted to complete in mid of December," he stated.