Friday, September 13th 2019 Reporter: Rezki Apriliya Iskandar Translator: Maria Inggita 1046
(Foto: Rezki Apriliya Iskandar)
Senen Sub-district Bina Marga Unit Head, Irfanuddin deployed 13 personnel to elevate collector road located at Gang XIV, RW 04, Kramat, Senen.
Road is always submerged in puddles when it rains
"Road is always submerged in puddles when it rains. Thus we need to elevate the road," he explained, Thursday (9/12).
For information, this road has length 200 meters and width 1.5 meters. His side uses scrap and hot mix asphalt for road paving.
"It will be elevated around 30 centimeters. We use one baby roller to help hardening the asphalt," he explained.
Currently, around 75 meters of the road has been elevated. It actually needs around one week to complete road elevation work but his side needs to do other work first.
"We need to elevate waterway first," he asserted.