Lamp Installation at Corridor XIII Has Reached 80 Percent

Monday, September 24th 2018 Reporter: Aldi Geri Lumban Tobing Translator: Nugroho Adibrata 823

Pengerjaan Penerangan di Koridor XIII Sudah 80 Persen

(Foto: doc)

Lamp installation at the top is already installed wholly

The lamp installation at the top and bottom of Transjakarta bus plying Corridor XIII (Ciledug-Tendean) has reached 80 percent.

Jakarta Industry and Energy Dept. Head, Yuli Hartono expressed that installation of panel and ceiling lamp installation at the bottom of the flyover is still ongoing.

"Lamp installation at the top is already installed wholly," he expressed, Monday (9/24).

It is hoped that the user and officer of the bus could be more secure and comfortable.

"Besides that, we also want motorists passing under the elevated corridor XIII to get adequate lighting," he explained.

South Jakarta Industry and Energy Head, Suryanto added that 659 points of ceiling lamp powered 120 watts are planned to be installed at the bottom of the corridor.

"From that number, 530 out of them have been installed. Predictably, this project will be complete in the forthcoming November," he stated.

As for the information, the number of lamps on the elevated track of corridor XIII totaled 300 points powered 200 watts plus 11 points of two-branched pole. Then for lighting lights at the bottom of the elevated track installed in 130 points powered 120 watts.