Tanah Abang Skybridge Project Has Touched 25 Percent

Friday, September 14th 2018 Reporter: Rezki Apriliya Iskandar Translator: Nugroho Adibrata 1239

Pembangunan Skybridge Tanah Abang Capai 25 Persen

(Foto: doc)

Tanah Abang Skybridge project has touched 25 percent

The development progress Tanah Abang Skybridge or crossing bridge has now reached 25 percent. It is including installation of steel material in zone A and floor installation.

"Tanah Abang Skybridge project has touched 25 percent," expressed Yoory C Pinontoan, Director Presidential of PD Pembangunan Sarana Jaya, Friday (9/14).

He explained that the development that spent Rp 35.8 billion has entered Zone B with pedestal casting and foundation work, assembly or installation of steel structure buildings and second floor.

 

The total length of steel material that has been installed is around 187 meters with 12 meters height. For work on the second floor, concrete that has been installed is approximately 115 meters.

He added that the 80 percent of bridge development is carried out at the factory using knock down systems, namely steel frames and structures made separately from the work site.

"Hopefully the bridge that is able to accommodate 446 street vendors can operate on October 15, 2018," he said.