Monday, February 26th 2018 Reporter: Wuri Setyaningsih Translator: Nugroho Adibrata 1571
(Foto: Wuri Setyaningsih)
Central Jakarta Bina Marga Sub-dept. is repairing a manhole cover of the water channel on Jalan Pasar Senen that collapsed up to six meters.
Currently six officers began to repair the channel
Muhammad Rohman, Executing Unit Head of Senen Sub-district Water Resources justified the water channel on Jalan Pasar Senen was collapsed up to 6 meters on Saturday (2/24) due to heavy equipment load.
"Besides that, the channel's sheet pile was also collapsed. Currently six officers began to repair the channel," said Muhammad Rochman, Executing Unit Head of Bina Marga, Senen Sub-district, Monday (2/26).
The channel work is including sheet pile repair and manhole cover installation. The repair itself is predicted to be completed within a week.