Thursday, October 19th 2017 Reporter: Rudi Hermawan Translator: Nugroho Adibrata 1416
(Foto: Rudi Hermawan)
The neighborhood roads repair in North Seribu Islands Sub-district will be executed soon. Material that will be used is already on the way towards Panggang Island, Kelapa Island, Harapan Island and Kelapa Dua Island.
We've made a contract with the worker. The material is still on the way and will arrive tomorrow
"We've made a contract with the worker. The material is still on the way and will arrive tomorrow," said Toto Bondan, Head of North Seribu Island Sub-district, Thursday (10/19).
Bondan explains total wide of the repair will take 7,500 square meters. It will spend around Rp 3.692 billion.
"It's targeted to be finished in the upcoming December. Hopefully all can run smoothly," he closed.