Sentiong River Dredging Targeted to Complete in August

Thursday, August 4th 2016 Reporter: Aldi Geri Lumban Tobing Translator: Rizky Mawardi 1678

Pengerukan Kali Sentiong Ditargetkan Rampung Akhir Agustus

(Foto: Aldi Geri Lumban Tobing)

Jakarta Dept. of Water Management conducts dredging for Sentiong river at Jalan Paru-Paru Kampung Bahari, Sunter Agung Urban Village, Tanjung Priok. Two amphibious PC 200 are deployed to dredge the river.

The mud thickness reaches three meter

Adrian Mara Maulana, Head Section of East Flow Maintenance for Jakarta Dept. of Water Management, said the river faces sedimentation. The river will be dredged along one kilometer and five meter of depth.

“The mud thickness reaches three meter,” he said.

It is hoped the dredging will solve puddle at Pademangan Timur, Kampung Bahari, Sunter Agung Urban Village, Tanjung Priok and Kemayoran, Central Jakarta.

“It is targeted to complete in August,” he closed.